A long and winding road project: city staff explain why roadwork takes time

The Carrboro council and city staff held a workshop on April 8 on budget plans for fiscal year 2026, which starts July 1 2025.

 GOVERNMENT

By Fraser Sherman
Correspondent

CARRBORO–Completing road projects is a slow process that can even leave elected officials wondering if anything is happening at all.

At Tuesday’s Carrboro Town Council meeting, Planning Director Tina Moon broke down the town’s ongoing road and transportation projects: which ones are funded; which ones are applying for funds; and the schedule for completing them.

For instance, the town plans two pedestrian-activated crossings along NC Highway 54. City documents say the crossings will be located at high-use transit stops. Busy, though 54 is, pedestrians frequently cross the road to reach the buses. City staff expect the state Department of Transportation to advertise for bids in April, with construction to start this summer.

“This is a real win,” said Moon, because the crossings are badly needed for community safety.

Another project would install bike loop detectors at downtown intersections to advance the traffic lights if cyclists are in the road. The contractor who won the bid process is currently preparing surety bond and insurance information before the work goes any further.

Carrboro’s planned bicycle and pedestrian improvements for Estes Drive are further behind, with design work tentatively scheduled to begin this summer. The DOT has told Carrboro to budget for higher costs than the original estimates because of right-of-way and utility easement problems. Carrboro is working on alternative alignments for the pathways in case the cost is too high.

“I’m sure you hear from folks asking why you haven’t moved forward (on various projects),” Moon told the council. All sorts of delays can prolong the process: a landowner doesn’t want to give the city an easement; a water line has to be replaced or moved; there’s heavy competition for funding sources. Working with the DOT and identifying which projects can get funding is a skill. “We’re continuing to look for sources for projects that have been identified as priorities.”

Calming traffic

Moon said city staff have caught up on a backlog of requests for traffic-calming measures. There are roughly 14 applications on their plate and half of them are at various points in the approval process.

One of the applications won town council approval Tuesday night. Two years ago, residents of the Kent Woodlands neighborhood asked Carrboro to install traffic-calming measures on Rossburn Way. Concerns included: near misses between cars and children; that 25 MPH is too fast for Rossburn; drivers frequently exceed that speed, and drivers often ignore the Rossburn/Palomar Court stop sign.

The council voted unanimously for a resolution to: install a crosswalk and signage near 301 Rossburn; lay down a double yellow line along the curve near 413 Rossburn; and analyze whether these measures did the trick.

Moon said city staff were looking at ways to improve the process for requesting traffic-calming measures. For example, she said the petition process pushes residents who want speed tables on their street to negotiate with neighbors who don’t. If the council thinks Carrboro needs a different approach, city staff can look at alternatives.

Some residents, Moon said, want narrower streets to calm traffic down. That’s a problem since the fire department requires a minimum width to ensure they can get their trucks to an emergency. “The fire department has made it clear they need 20-foot-wide clearance,” which raises problems with older, narrower streets with parking along one side. Even if everyone on the street wants a narrower roadway, it may not be an option.


Fraser Sherman has worked for newspapers, including the Destin Log, the Pensacola News-Journal and the Raleigh Public Record. Born in England, he’d still live in Florida if he hadn’t met the perfect woman and moved to Durham to marry her. He’s the author of several film reference books and has published one novel and several short story collections. This reporter can be reached at: Information@TheLocal Reporter.press.