GROWTH & DEVELOPMENT
By Adam Powell
Correspondent
CHAPEL HILL – On the evening of June 11, the Chapel Hill Council received an update and discussed the progress of the North-South Bus Rapid Transit (NSBRT) project, which has reached the 60% design phase. The project aims to begin construction in 2027 and complete it in 2029.
The project will feature 17 premium stations, 5.7 miles of bus-only lanes, and seven-day service, including extended hours during school sessions. The project also includes significant mobility improvements, such as a completed sidewalk network and multi-use paths.
“So for those who are unaware of what the NSBRT is, if you’ve ever ridden the NS (North-South) bus as it exists today, that’s essentially what it’s going to be,” said Katie Fontaine, Transit Development Manager at Chapel Hill Transit who is serving as leader and manager of the NSBRT project.
“It’s going to go from Eubanks (Road) to Southern Village, which is an 8.2-mile corridor,” continued Fontaine. “Of that corridor, 5.7 miles is going to be bus-only lanes, where the bus will be separated from mixed traffic, and be able to travel much faster. Throughout that corridor, we’ll have 17 premium station areas with enhanced amenities for customer experiences, so they’ll look a little bit different from your standard that exists today on the side of the road.”
“We’ll have seven-day service with longer hours,” added Fontaine. “We’re looking to go until about 11 o’clock at night, and even until 1 a.m. when school’s in session Friday and Saturday. You’ll have shorter wait times.”
While the town currently has a transit app in place, Fontaine expressed optimism that, given the speed of the bus through town, wait times will ideally be less than ten minutes for local commuters and riders. The project also aims to make mobility easier for local walkers and bicyclists traversing the area.
“We have our lovely transit app,” explained Fontaine. “Hopefully, with BRT you won’t have to pull out that app because within six to seven minutes the bus will be there, and then we’ll also have mobility improvements. For those who aren’t riding the bus but are still traveling along the corridor, we’ll be completing the sidewalk network on one side of the street, and the other side will have a multi-use path for our pedestrians and cyclists to use as well.”

The NSBRT project has entered the fourth and final phase of progress. The initial phase–the first 5% of the project–focused on identifying the specific corridor for the transit line and general station areas. Phase two–30% of the design–concentrated on refining the station locations, defining the corridor, and receiving clearance from NEPA (the National Environmental Policy Act).
The third phase of the project, marking 60% completion of the design, involved finalizing station dimensions, footprints, and design, as well as finalizing the corridor’s right-of-way. Each of those three steps has been completed.
The fourth and final phase, which will take place over the next couple years, involves finalizing the design and construction details, such as materials, colors, and utilities, while also coordinating with various third parties as construction prepares to start around 2027.
Now that the third phase has been completed and 60% of the design phase is concluded, the Town of Chapel Hill is coordinating with the North Carolina Department of Transportation on various aspects of the proposed project, such as: cost-sharing agreements and construction management expertise; collaboration with town-led projects and local developments; plus discussions with the University of North Carolina and UNC Health about station designs and the roadway improvements that will be necessary. Finally, NSBRT is also continuing community engagement efforts with local property owners adjacent to the proposed corridor, as well as with businesses that may be affected by the project and its construction over the next two to four years.
Next steps for the NSBRT project include: finalizing design; requesting a grant from the Federal Transit Administration (FTA); and completing FTA-mandated risk and readiness reviews. Those events, along with executing necessary agreements and finalizing the project’s engineering, will take place over the final six months of 2025.
In 2026, right-of-ways will be acquired, along with the necessary permitting. There will also be a necessary relocation of certain utilities along the NSBRT corridor, as well as executing the FTA grant agreement, and then going through the construction bid and contract process. If the project can begin construction in 2027, it will be able to launch its service in approximately four years, in 2029.
Funding challenges were acknowledged in the discussion among council members, with a $114.1 million funding request pending to the United State Congress. That funding will be absolutely vital for the project to move forward on its current timeframe.
“I love that you are so enthusiastic about this project,” said council member Amy Ryan to Fontaine. “You clearly love this project. And I love that we’re talking about 2027 and 2029 but the federal landscape has really changed. So can you speak a little bit to the things you’re thinking about as you’re watching that unfold, and what probably is four years of a little bit rougher funding environment?”
“We’ve been in close contact with our federal contacts,” said Fontaine in response to Councilwoman Ryan. “We actually had a call with them (on June 10) to kind of start talking about the project. They’re using the same phrase I am, which is cautiously optimistic. We are going to keep moving with this project at the schedule that we have–in the timeline we have–until we are told otherwise. Everything that they’ve been saying to us has been telling us to stay the course as well. They don’t see any issues with our schedule at this time, or with us looking to apply for that federal grant going into next year. So at this point in time, we’re not concerned about that. We’re just going to a wait-and-see kind of approach.”
“I wanted to say thank you for this. Thank you for this update,” added council member Camille Berry. “Thank you for helping us to understand that we can keep moving forward. I’m actually a little bit more than cautiously optimistic, because that’s my nature. I really appreciate this and, Katie, I’m really grateful for your attention to this project.”
“I just attended a Vision Zero Leadership Institute with council member (Paris) Miller-Foushee, and this will go far to helping us achieve that,” continued Berry. And for those who need a reminder, Vision Zero is, at its core, to make it safer for people. The team helped me understand that, but it’s how to make it safe for all, especially pedestrians and non-motorized people who are moving around: to do so safely.”
“I think we’re good to go,” added Mayor Jessica Anderson. “Thank you for hanging in there; fingers and toes crossed. Thank you for all your continued hard work. It’s a really important project.”

Adam Powell has been a correspondent for The Local Reporter since 2023. A 2001 graduate of UNC-Chapel Hill, Powell has served as managing editor of multiple local publications, including the News of Orange County, the Mebane Enterprise, the Caswell Messenger, and the ACC Sports Journal. Powell has won more than 20 North Carolina Press Association Awards throughout his journalism career for Excellence in Education Reporting, Excellence in Sports Columns and Features, and Excellence in Video Production. He has also been recognized by the North Carolina School Public Relations Association (NCSPRA) for Excellence in Education Writing and for his newsletters representing Rockingham County Schools and the North Carolina Cyber Academy. The author of four books. Adam currently resides in Mebane with his wife Julie and children Colt and Jenna. This reporter can be reached at:Information@TheLocal Reporter.press