OWASA highlights emergency response in Western North Carolina post-Helene

COMMUNITY NEWS

By Adam Powell
Correspondent

CHAPEL HILL–At its February 13 monthly meeting, the Orange Water and Sewer Authority (OWASA) highlighted its support to the emergency response in North Carolina,  post-Hurricane Helene.

Jesse DuClau, Director of Distribution & Collection for OWASA, explained the organization’s work in repairing damaged infrastructure and ensuring water service restoration, highlighting team collaboration, and resilience. OWASA spent hundreds of hours in the western part of the state in the fall, providing critical resources and expertise to help that particular area of the state bounce back from one of the worst natural disasters in its history.

DuClau discussed the logistical challenges and repairs in areas such as Black Mountain, Asheville, and Beech Mountain, including service line transfers and repairs on water mains of various sizes. OWASA’s team coordinated with Fayetteville PWC and other utilities to restore water service to stricken areas. A second deployment focused on valve and service repairs, including inspecting water meters and isolation valves. In addition, OWASA assisted the Asheville Water Treatment Plant in lifting a “boil water” advisory.

“OWASA stepped up to help our neighbors in North Carolina. It was a rewarding experience. It brought our teams together in a way that’s really difficult to describe. We were proud of the work that we did. We were proud to be there helping our neighbors. We were able to utilize our knowledge and experience, not only to help our communities in North Carolina but help us find ways to be more resilient in our emergency response,” explained DuClau.

Hurricane Helene came through Florida as a category-four hurricane in late September. By the time it got to North Carolina, it was a tropical storm with approximately 50—to 75-mile-per-hour winds. Over a period of three days, rainfall totals of up to 30 inches fell in western North Carolina. The Swannanoa and French Broad Rivers crested about 25 feet above normal, and nearly 2,000 landslides were reported, along with 104 confirmed fatalities and an estimated $59 billion of damage in North Carolina alone.

“In the aftermath of the storm, our team (like most of our peer organizations) were eager to find ways to help,” explained DuClau further. “It was evident early on that there was a need for utility assistance, but the conditions were still dangerous. Access was limited and logistically difficult to find ways that we could assist. So we started with the state EOC (Emergency Operations Center) staff in the critical infrastructure desk, through the North Carolina WaterWARN.

NCWaterWARN is a statewide water and wastewater agency response network comprised of local utilities committed to providing emergency assistance when the need arises. OWASA has been a member of NCWaterWARN since 2017 and received requests for labor, equipment, materials, and other resources needed from utilities impacted by Hurricane Helene. OWASA joined forces with peer utilities such as the aforementioned Fayetteville PWC, which volunteered their time and resources to help restore water and wastewater services to impacted areas. 

“After visiting the area, we understood the need, the logistical challenge, and getting materials on the ground,” added DuClau. “We mobilized a team of OWASA employees to provide labor and equipment to the Black Mountain area. They still didn’t have water service, so our goal was to focus on the distribution system. We teamed up with Fayetteville PWC and provided three crews to locate and repair the damaged infrastructure.”

OWASA repairs, relocates water mains in Black Mountain

DuClau indicated that most of the water infrastructure damage was due to heavy erosion around the rivers and landslides. OWASA worked with the Black Mountain team to develop a plan to prioritize and address the most critical needs first as they worked to restore water service in their area.

“We performed multiple repairs, including locating and repairing damaged one-and-a-half-inch to 10-inch water mains. We did service line transfers to restore service to businesses and residential customers, and we repaired damaged mains to eroded creek areas. A lot of the repairs we did were on one-and-a-half-inch to 10-inch mains. Service line transfers were to restore services to customers and businesses.”

DeClau explained that OWASA worked with the Black Mountain team to unload water lines that were received from various utilities all over North Carolina. OWASA coordinated with those utilities and delivered emergency repair materials from OWASA’s inventory, along with Fayetteville PWC and Durham Water Management, to the Black Mountain community.

He went into further detail about the many logistical challenges working in the mountains with limited infrastructure, damaged roadways, and numerous safety hazards.

“There was a lot of difficult terrain (and) difficult access,” stated DeClau. “The water levels (in the creeks and rivers) were still questionable, so being safe and making sure that we were taking all necessary precautions to address hazards was important to our team.”

Among the specific fixes undertaken by the OWASA team in collaboration with other state utilities was relocating damaged water mains to intact mains. OWASA helped install new water service and abandoned a damaged water main that feeds the western end of Black Mountain.

OWASA also worked to make a significant repair to a six-inch water main that had a large hole in it from the Swannanoa River. That particular repair, which restored a tank site, was completed in a difficult area with steep terrain adjacent to the I-40 freeway. 

“We had to do that repair underwater, because we were unable to divert the water away from us,” explained DuClau.

OWASA also worked with PWC crews to build an earthen dam in the Swannanoa River to isolate and repair a 10-inch transmission water main.

“(What was) difficult here was the (water) main was about four to five feet deep (under the river), and we were unable to access it without building this dam. We utilized a lot of the eroded materials that were around the creek, and that’s what we used to build that earthen dam. We dewatered the area where the leak of the 10-inch main was.”

Second deployment to Black Mountain focused on water service

Following OWASA’s initial deployment and performing repairs of the larger water mains in Black Mountain’s local distribution system, a second deployment to Black Mountain focused more on the water service within the local neighborhood.

“The second deployment crew, they focused on performing valve and service repairs and restorations, including locating, excavating, inspecting, and operating 150 water meters and 90 isolation valves,” continued DuClau. “A lot of these areas were eroded and had heavy debris around them, so locating them and finding them using maps and things that we were provided from Black Mountain was a big challenge.”

OWASA backfilled and restored several heavily-eroded areas–some so eroded that the water main was exposed out of the ground.

“We backfilled and restored it to protect those mains when they were re-energized,” said DuClau. “I was overwhelmed by the number of people who volunteered to deploy. We had enough people to set up and do this work for seven more weeks after we were done. However, our assignment was complete in this area. Once the water was restored, we demobilized and returned home.”

OWASA assists Asheville with lab testing, water quality sampling

Shortly after OWASA’s second deployment, the city of Asheville requested some assistance in the lab through the NCWaterWARN desk. Again, OWASA stepped up, providing labor and resources to temporarily relieve the Asheville WTP laboratory compliance team.

OWASA performed distribution system water quality sampling and analyzed profiles for surface water quality at North Fork and Bee Tree Reservoirs. They also performed laboratory analyses of supplemental water quality parameters.

“(OWASA staff members) Izzy Garrity and Simon Lobdell teamed up with Davidson Water (Inc.) to provide labor and resources to relieve the Asheville Water Treatment Plant laboratory compliance team,” added DuClau. “This deployment was about 13 days, I believe. The Asheville water team had been working for weeks on end to attempt to restore potable water service to the Asheville service area and the surrounding communities, including Black Mountain–Black Mountain gets a portion of their water from Asheville.”

Speciality equipment assists Beech Mountain with storm recovery

A few weeks following the Asheville deployment, Beech Mountain contacted the NCWaterWARN desk for assistance in their outfalls and requested specialty equipment to work with the steep terrain in that area. Once again, OWASA quickly responded to provide the necessary services.

“Dennis Kaebisch, our preventative maintenance supervisor, formed a team and deployed our recently purchased off-road sewer inspection equipment,” explained DuClau. “It’s an off-road UTV that’s used to get into some of these tight areas.”

OWASA used cameras and inspected approximately 15,000 linear feet of sewer mains along the steep terrain of the Beech Mountain sewer system, finding numerous trouble spots that needed maintenance and repairs.

“We found things like damage and missing sewer pipe,” said DuClau. “We found blockages where the pipe was full of rocks, dirt, and debris. We did locate some sanitary sewer overflows, and worked with the Black Mountain team to address those. And then we found some manholes that were missing, which were covered with dirt, debris, and rocks. Access wasn’t easy before, but when all this erosion happened, it made it even more difficult.

In total, DuClau mentioned that 27 staff members and 25 pieces of equipment were deployed, and over 1,500 hours were worked.

“Our team was proud of the work that we did. It helped increase our morale and also prepared us if this situation ever comes to us in the future.”

OWASA staff received praise from members of their board of directors for their call to duty and their diligent efforts to help their fellow citizens in the western part of the state.

“At the winter meeting of the metro mayors (NC Metro Mayors Coalition Winter Meeting) in Wilmington (in December), OWASA was called out over and over again for the exceptional work that you all did in western North Carolina,” said board member Susana Dancy. “The word came to me that they heard OWASA being complimented more than any other particular entity. So, I just wanted to let you know that this team made a great impression statewide as a helper and a resource. And I want to make sure that you all know that. Thank you very much.”


Adam Powell has been a correspondent for The Local Reporter since 2023. A 2001 graduate of UNC-Chapel Hill, Powell has served as managing editor of multiple local publications, including the News of Orange County, the Mebane Enterprise, the Caswell Messenger, and the ACC Sports Journal. He also served as a publisher in the rivals.com network, running the UNC (TarHeelIllstrated.com) and Wake Forest (DeaconsIllustrated.com) websites. In 2022, Powell teamed with famed sports journalist Tom Rinaldi of ESPN and Fox Sports for a podcast on the life of deceased former MLB player Lyman Bostock (https://www.foxsports.com/shows/tom-rinaldi-presents/episodes).

Powell has won more than 20 North Carolina Press Association Awards throughout his journalism career for Excellence in Education Reporting, Excellence in Sports Columns and Features, and Excellence in Video Production. He has also been recognized by the North Carolina School Public Relations Association (NCSPRA) for Excellence in Education Writing and for his newsletters representing Rockingham County Schools and the North Carolina Cyber Academy. The author of four books. Adam currently resides in Mebane with his wife Julie and children Colt and Jenna. This reporter can be reached at: Information@TheLocal Reporter.press